1Z0-489 · Question #48

Before turning the system over to a customer, you want to verify that both SPs are functional. Which action do you perform to test the failover?

See the full explanation below for the reasoning.

Question

Before turning the system over to a customer, you want to verify that both SPs are functional. Which action do you perform to test the failover?

Options

  • ASet /SP/failover on.
  • BStart /SP/failover.
  • CSet /SP/redundancy failover=true.
  • DSet /SP/redundancy initiate_ failover_ action=true Answer: D