nerdexam
Oracle

1Z0-448 · Question #44

Your project requires a loop through the same package logic 24/7. You must be able to purge those executions when required. How do you accomplish this? (Choose the best answer.)

The correct answer is B. Create a scenario from the package, add the scenario as the last step in the package, run it. See the full explanation below for the reasoning.

Question

Your project requires a loop through the same package logic 24/7. You must be able to purge those executions when required. How do you accomplish this? (Choose the best answer.)

Options

  • ALink the last step of the package to its first step to create an infinite loop.
  • BCreate a scenario from the package, add the scenario as the last step in the package, run it
  • CCreate a scenario from the package, add the scenario as the last step in the package, run it
  • DDrag the package to the last step in the package, run it asynchronously, and then save.

How the community answered

(36 responses)
  • A
    14% (5)
  • B
    75% (27)
  • C
    3% (1)
  • D
    8% (3)

Community Discussion

No community discussion yet for this question.

Full 1Z0-448 Practice