You are designing a load plan in which you must run Mappings A and B one after the other while running Mapping C at the same time. Which option represents the steps to accomplish this? (Choose the…

The correct answer is C. Add a parallel step, add two parallel steps underneath it, then add A and B to one parallel step. (https://docs.oracle.com/middleware/1212/odi/ODIDG/loadplans.htm#ODIDG1356)

Executing and Monitoring Integrations

Question

You are designing a load plan in which you must run Mappings A and B one after the other while running Mapping C at the same time. Which option represents the steps to accomplish this? (Choose the best answer.)

Options

  • AAdd a parallel step, add three serial steps underneath it, then add A to the first parallel step, B to
  • BCreate a scenario from the variable and add the scenario to the load plan to create a case step.
  • CAdd a parallel step, add two parallel steps underneath it, then add A and B to one parallel step,
  • DAdd a parallel step, add two serial steps underneath it, then add A and B to one serial step, and C

How the community answered

(47 responses)
  • A
    6% (3)
  • B
    4% (2)
  • C
    74% (35)
  • D
    15% (7)

Explanation

(https://docs.oracle.com/middleware/1212/odi/ODIDG/loadplans.htm#ODIDG1356)