You are designing a load plan in which you must run Mappings A and B one after the other while running Mapping C at the same time. Which option represents the steps to accomplish this? (Choose the…
The correct answer is C. Add a parallel step, add two parallel steps underneath it, then add A and B to one parallel step. (https://docs.oracle.com/middleware/1212/odi/ODIDG/loadplans.htm#ODIDG1356)
Executing and Monitoring Integrations
Question
You are designing a load plan in which you must run Mappings A and B one after the other while running Mapping C at the same time. Which option represents the steps to accomplish this? (Choose the best answer.)
Options
- AAdd a parallel step, add three serial steps underneath it, then add A to the first parallel step, B to
- BCreate a scenario from the variable and add the scenario to the load plan to create a case step.
- CAdd a parallel step, add two parallel steps underneath it, then add A and B to one parallel step,
- DAdd a parallel step, add two serial steps underneath it, then add A and B to one serial step, and C
How the community answered
(47 responses)- A6% (3)
- B4% (2)
- C74% (35)
- D15% (7)
Explanation
(https://docs.oracle.com/middleware/1212/odi/ODIDG/loadplans.htm#ODIDG1356)