Oracle
1Z0-347 · Question #32
Which change mode takes a snapshot at the stages mentioned below: - When the orchestration process starts - When a change order is received at an orchestration process step
The correct answer is A. Incremental. See the full explanation below for the reasoning.
Question
Which change mode takes a snapshot at the stages mentioned below:
- When the orchestration process starts
- When a change order is received at an orchestration process step
Options
- AIncremental
- BSimple
- CNone
- DAdvanced
How the community answered
(33 responses)- A85% (28)
- B3% (1)
- C9% (3)
- D3% (1)