1Z0-347 · Question #17

Which process requires the Release Planning recommendation process to be executed manually so that a supply order gets created?

The correct answer is C. Back-to-Back Order. See the full explanation below for the reasoning.

Question

Which process requires the Release Planning recommendation process to be executed manually so that a supply order gets created?

Options

  • AManual orders using File Based Data Load
  • BMin-Max planning replenishing a transfer order
  • CBack-to-Back Order
  • DDrop Ship Order
  • EMin-Max planning replenishing a purchase request

How the community answered

(20 responses)
  • B
    5% (1)
  • C
    75% (15)
  • D
    15% (3)
  • E
    5% (1)

Community Discussion

No community discussion yet for this question.