Which three statements are true about the file-based import process? (Choose three.)
The correct answer is B. You can create a mapping before creating an import job. D. An import job references an import object that represents the structure of the interface table. Explanation/Reference: B: When you create an import activity, you must specify a mapping of the fields in your file to the attributes of the import object. You can create the mapping while creating an import activity or separately using the Manage File Import Mappings task. The…
Question
Which three statements are true about the file-based import process? (Choose three.)
Options
- AThe data that you import must be in a spreadsheet.
- BYou can create a mapping before creating an import job.
- CAn import job must be run immediately.
- DAn import job references an import object that represents the structure of the interface table.
- EThe data that is being imported should include references to the system from which the data is
How the community answered
(48 responses)- A6% (3)
- B81% (39)
- C10% (5)
- E2% (1)
Explanation
Explanation/Reference: B: When you create an import activity, you must specify a mapping of the fields in your file to the attributes of the import object. You can create the mapping while creating an import activity or separately using the Manage File Import Mappings task. The mapping is stored and managed as a separate object. D: The import object defines the information for importing external data into the specified business component. The import objects you select when you create an import activity are provided by Oracle. Not C: You can schedule to run the import at a time you specify or run it immediately