Oracle
1Z0-330 · Question #32
After the compensation plan was configured, the Validate Plan Setup process was run successfully with no warnings or errors. However, when the worksheet is accessed by a Line Manager, the Line…
The correct answer is B. The compensation administrator did not run the Validate Plan Setup process and run. See the full explanation below for the reasoning.
Question
After the compensation plan was configured, the Validate Plan Setup process was run successfully with no warnings or errors. However, when the worksheet is accessed by a Line Manager, the Line Manager notices that employees who are ineligible are also visible in the worksheet despite running the Validate Plan Setup process. What is the reason for this? (Choose the best answer.)
Options
- AThe Validate Plan Setup process does not validate eligibility profiles.
- BThe compensation administrator did not run the Validate Plan Setup process and run
- CThe Validate Plan Setup process failed to report errors from the eligibility profiles.
- DThe Validate Plan Setup process showed a warning about errors on the eligibility profiles, which
How the community answered
(33 responses)- A3% (1)
- B76% (25)
- C12% (4)
- D9% (3)
Community Discussion
No community discussion yet for this question.