Oracle
1Z0-1074-20 · Question #64
Assume today is November 15, 2015, and you are getting ready to implement new standard costs for the new year Your cost planning scenario has a January 1, 2016 effective date. An item has three work…
The correct answer is D. You will receive an error because the application will detect that all three are plausible, and it will be. Explanation/Reference:
Manage Item Costs
Question
Assume today is November 15, 2015, and you are getting ready to implement new standard costs for the new year Your cost planning scenario has a January 1, 2016 effective date. An item has three work definitions. One work definition has an October l, 2015 effective date. A second work definition has a December 1, 2015 effective date. A third work definition has a January 2, 2016 effective date. How will the application select the work definition?
Options
- AIt will use the work definition with the January 2, 2016 effective date.
- BDepending on the selection criteria, it will use the work definition with the December l, 2015 effective
- CIt must always use the work definition with the October 1, 2015 effective date.
- DYou will receive an error because the application will detect that all three are plausible, and it will be
How the community answered
(55 responses)- A5% (3)
- B2% (1)
- C11% (6)
- D82% (45)
Explanation
Explanation/Reference:
Topics
#work definition#effective date#cost planning scenario#standard cost rollup
Community Discussion
No community discussion yet for this question.