Oracle
1Z0-1074-20 · Question #46
Which four steps need to be completed to establish standard costs for a make item?
The correct answer is A. Run preprocessor. B. Complete cost roll-up. C. Publish costs D. Export item costs. Explanation/Reference:
Manage Item Costs
Question
Which four steps need to be completed to establish standard costs for a make item?
Options
- ARun preprocessor.
- BComplete cost roll-up.
- CPublish costs
- DExport item costs.
- EAdd standard costs to a cost scenario.
- FCreate a new cost scenario.
How the community answered
(41 responses)- A76% (31)
- E10% (4)
- F15% (6)
Explanation
Explanation/Reference:
Topics
#standard costs#make item#cost rollup#cost scenario