Scenario: A Citrix Architect needs to manage the disaster recovery process for a XenApp and XenDesktop environment. The environment currently consists of an active datacenter which is typically…

The correct answer is B. Block access to primary datacenter, terminate/drain existing sessions, complete replication, reverse. Explanation/Reference: Go/No-Go Decision Terminate existing sessions Finish replication

Manage and Monitor a Citrix Virtual Apps and Desktops Solution

Question

Scenario: A Citrix Architect needs to manage the disaster recovery process for a XenApp and XenDesktop environment. The environment currently consists of an active datacenter which is typically accessed by users and a disaster recovery (DR) datacenter which would be used in the event that a disaster impacts the primary datacenter. The organization has made it a priority to minimize the loss of data when failing over between datacenters and has begun planning for an event in which the environment must fail over from the primary datacenter to the DR datacenter. What is the appropriate sequence of steps that the architect should follow after getting management approval to complete the process in case of such an event?

Options

  • ABlock access to primary datacenter, complete replication, terminate/drain existing sessions, reverse
  • BBlock access to primary datacenter, terminate/drain existing sessions, complete replication, reverse
  • CTerminate/drain existing sessions, complete replication, block access to primary datacenter, enable
  • DComplete replication, terminate/drain existing sessions, block access to primary datacenter, reverse
  • EComplete replication; block access to primary datacenter, terminate/drain existing sessions, enable
  • FTerminate/drain existing sessions; block access to primary datacenter, complete replication, reverse

How the community answered

(45 responses)
  • A
    2% (1)
  • B
    80% (36)
  • C
    2% (1)
  • D
    11% (5)
  • F
    4% (2)

Explanation

Explanation/Reference: Go/No-Go Decision Terminate existing sessions Finish replication

Topics

#disaster recovery#failover sequence#datacenter replication#session management