Scenario: A Citrix Architect needs to manage the disaster recovery process for a XenApp and XenDesktop used and a disaster recovery (DR) datacenter which would be used in the event that a disaster…
The correct answer is A. Complete data replication from the primary datacenter to the DR datacenter. D. Codifier data replication from the DR datacenter to the primary datacenter. E. Drain existing sessions from the primary datacenter. Explanation/Reference: Steps before allow access to DR Datacenter if Active Data Center becomes passive is: 1. Go/No-Go Decision 2. Block access to environement 3. Terminate existing connections 4. Finish replication 5. Reverse direction of replicaton
Question
Scenario: A Citrix Architect needs to manage the disaster recovery process for a XenApp and XenDesktop used and a disaster recovery (DR) datacenter which would be used in the event that a disaster impacts the primary datacenter. The overall environment has been designed to actively replicate user data and application data from the primary datacenter recovery datacenter using Microsoft DFS-R. Management has made it a proirity to minimize the loss of data when failing over between datacenters. Due to an earthquake, the primary datacenter suffers a major outage that affects multiple components. Management has decided to fail over the DR datacenter, and the architect has blocked access to the primary datacenter to prevent new attempts to connect to the XenApp and XenDesktop Site there. Which three actions must the architect perform to meet the company priorities before enabling access to the DR datacenter? (Choose three.)
Options
- AComplete data replication from the primary datacenter to the DR datacenter.
- BMonitor the automated failover process.
- CTransport backup data repositories to the DR datacanter.
- DCodifier data replication from the DR datacenter to the primary datacenter.
- EDrain existing sessions from the primary datacenter.
- FEvaluate the condition of the XenApp and XenDesktop environment in the primary datacenter.
How the community answered
(65 responses)- A80% (52)
- B12% (8)
- C3% (2)
- F5% (3)
Explanation
Explanation/Reference: Steps before allow access to DR Datacenter if Active Data Center becomes passive is: 1. Go/No-Go Decision 2. Block access to environement 3. Terminate existing connections 4. Finish replication 5. Reverse direction of replicaton