nerdexam
CIW

1D0-510 · Question #22

Which of the following is a contract used in project management that outlines the requirements for each project tier to ensure that the project objectives are met?

The correct answer is C. Statement of work (SOW). See the full explanation below for the reasoning.

Question

Which of the following is a contract used in project management that outlines the requirements for each project tier to ensure that the project objectives are met?

Options

  • AProject triangle
  • BOrganizational chart
  • CStatement of work (SOW)
  • DReturn on Investment (ROI)

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    80% (28)
  • D
    11% (4)

Community Discussion

No community discussion yet for this question.

Full 1D0-510 Practice