Brocade
143-085 · Question #26
You need to implement FC routing in your Gen 5 fabric. The backbone fabric will contain a factory default Brocade 7800 Extension Switch and a Brocade DCX 8510-8 with two FC16-32 blades. VEX_Port…
The correct answer is A. An Integrated Routing license must be installed on the Brocade 7800 Extension Switch. D. VEX_Ports must be configured on the Brocade 7800 Extension Switch. See the full explanation below for the reasoning.
Question
You need to implement FC routing in your Gen 5 fabric. The backbone fabric will contain a factory default Brocade 7800 Extension Switch and a Brocade DCX 8510-8 with two FC16-32 blades. VEX_Port connectivity to the edge fabrics will be needed in the final configuration. Which two statements describe how to enable the final configuration? (Choose two.)
Options
- AAn Integrated Routing license must be installed on the Brocade 7800 Extension Switch.
- BLSAN zones must be configured in the backbone.
- CVEX_Ports must be configured on the Brocade DCX 8510-8.
- DVEX_Ports must be configured on the Brocade 7800 Extension Switch.
How the community answered
(37 responses)- A70% (26)
- B22% (8)
- C8% (3)
Community Discussion
No community discussion yet for this question.