A critical database used for company operations cannot lose more than 15 minutes worth of data transactions. Which rule is being defined?

The correct answer is C. It is a recovery point objective. It defines the maximum acceptable loss of transaction activity. The requirement that no more than 15 minutes of transaction data may be lost defines your Recovery Point Objective (RPO) - i.e. the maximum acceptable data-loss window.

Backup Concepts and Planning

Question

A critical database used for company operations cannot lose more than 15 minutes worth of data transactions. Which rule is being defined?

Options

  • AIt is a recovery time objective. It identifies the limit to how many minutes of transactions can be
  • BIt is a recovery point objective. It identifies when the restore must be completed after the failure
  • CIt is a recovery point objective. It defines the maximum acceptable loss of transaction activity.
  • DIt is a recovery time objective. It identifies how fast the database must be recovered after a failure.

How the community answered

(60 responses)
  • A
    7% (4)
  • B
    15% (9)
  • C
    75% (45)
  • D
    3% (2)

Explanation

The requirement that no more than 15 minutes of transaction data may be lost defines your Recovery Point Objective (RPO) - i.e. the maximum acceptable data-loss window.

Topics

#RPO#RTO#data loss tolerance#SLA definitions