A planned failover of three VMs has just completed successfully, starting the VMs at the disaster recovery location. What next actions are available for the failover plan?
The correct answer is A. Undo, Start, Edit, Delete. After completing a planned failover for VMs to the disaster recovery site, the typical actions available in Veeam Backup & Replication for a failover plan are: Undo: This allows you to reverse the failover and return the VMs to the original location. Start: This would be used…
Question
A planned failover of three VMs has just completed successfully, starting the VMs at the disaster recovery location. What next actions are available for the failover plan?
Options
- AUndo, Start, Edit, Delete
- BUndo, Start, Copy, Delete
- CCancel, Start, Edit, Delete
- DCancel, Start, Copy, Delete
How the community answered
(50 responses)- A74% (37)
- B14% (7)
- C4% (2)
- D8% (4)
Explanation
After completing a planned failover for VMs to the disaster recovery site, the typical actions available in Veeam Backup & Replication for a failover plan are: Undo: This allows you to reverse the failover and return the VMs to the original location. Start: This would be used to initiate the failover plan if it needs to be executed again. Edit: This option permits modifications to the failover plan. Delete: This allows the removal of the failover plan if it is no longer needed. There are no options for Copy in the context of a failover plan, and the Cancel option is typically available before and during the failover process, not after completion.