A company needs to maintain and verify backups at a secondary site to meet the following requirements: RTO of two hours, RPO of 12 hours, four weeks retention. Which of the following backup copy job…

The correct answer is C. Periodic backup copy job, scheduled for a two-hour interval, with 112 restore points to retain. See the full explanation below for the reasoning.

Question

A company needs to maintain and verify backups at a secondary site to meet the following requirements: RTO of two hours, RPO of 12 hours, four weeks retention. Which of the following backup copy job configurations meets these requirements?

Options

  • APeriodic backup copy job, scheduled for a two-hour interval, with 56 restore points to retain
  • BPeriodic backup copy job, scheduled for a 12-hour interval, with 56 restore points to retain
  • CPeriodic backup copy job, scheduled for a two-hour interval, with 112 restore points to retain
  • DPeriodic backup copy job, scheduled for a 12-hour interval, with 112 restore points to retain

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    14% (4)
  • C
    79% (22)
  • D
    4% (1)