VDCD510 · Question #8
A DR project requires a recovery time objective (RTO) of 4 hours and has a recovery point objective (RPO) of 2 hours. The system fails at 8 p.m. on a Sunday evening. At what time is the application…
The correct answer is A. Midnight. The recovery time objective (RTO)--also known as the return to operation--is the amount of time it takes to restore a service after a failure has taken place. The recovery point objective (RPO) is the point in time to which the system needs to be restored following a failure…
Question
A DR project requires a recovery time objective (RTO) of 4 hours and has a recovery point objective (RPO) of 2 hours. The system fails at 8 p.m. on a Sunday evening. At what time is the application expected to be available to the end users?
Options
- AMidnight
- B10 p.m.
- C2 a.m.
- D11 p.m.
How the community answered
(59 responses)- A83% (49)
- B10% (6)
- C3% (2)
- D3% (2)
Explanation
The recovery time objective (RTO)--also known as the return to operation--is the amount of time it takes to restore a service after a failure has taken place. The recovery point objective (RPO) is the point in time to which the system needs to be restored following a failure. Chapter 3, RTO, RPO, and All That Stuff?