When considering incorporating redundancy into design, which of the following should be considered?

The correct answer is D. All of these are correct. The recovery time objective (RTO)--also known as the return to operation--is the amount of time it takes to restore a service after a failure has taken place. The recovery point objective (RPO) is the point in time to which the system needs to be restored following a failure…

Create a Design for vSphere 5.x Recoverability

Question

When considering incorporating redundancy into design, which of the following should be considered?

Options

  • AThe impact of the failure
  • BThe likelihood of the failure
  • CRTO and RPO values
  • DAll of these are correct

How the community answered

(25 responses)
  • A
    12% (3)
  • B
    8% (2)
  • C
    4% (1)
  • D
    76% (19)

Explanation

The recovery time objective (RTO)--also known as the return to operation--is the amount of time it takes to restore a service after a failure has taken place. The recovery point objective (RPO) is the point in time to which the system needs to be restored following a failure. In some cases a business may be interested in functionality and just assume items such as redundancy. The infrastructure qualities help consider aspects considered as good design.

Topics