VDCD510 · Question #117
You are VMware designer working at a company where a new business application is being rolled out. The SLA requirements are RTO of 2 hours and RPO of 10 minutes. During a project team meeting, the…
The correct answer is A. the application must be brought online and be accessible to users by 6 p.m. C. when the application is brought online, the data must be from a version as of 3:50 p.m. The recovery time objective (RTO)--also known as the return to operation--is the amount of time it takes to restore a service after a failure has taken place. The recovery point objective (RPO) is the point in time to which the system needs to be restored following a failure.
Question
You are VMware designer working at a company where a new business application is being rolled out. The SLA requirements are RTO of 2 hours and RPO of 10 minutes. During a project team meeting, the business user misunderstands this requirement. To illustrate the situation, you give an example where the system becomes unavailable at 4 p.m. To meet the project SLA, _____________. (Choose two)
Options
- Athe application must be brought online and be accessible to users by 6 p.m.
- Bthe application must be brought online and be accessible to users by 4:10 p.m.
- Cwhen the application is brought online, the data must be from a version as of 3:50 p.m.
- Dwhen the application is brought online, the data must be from a version as of 2 p.m.
How the community answered
(50 responses)- A72% (36)
- B20% (10)
- D8% (4)
Explanation
The recovery time objective (RTO)--also known as the return to operation--is the amount of time it takes to restore a service after a failure has taken place. The recovery point objective (RPO) is the point in time to which the system needs to be restored following a failure.
Topics
Community Discussion
No community discussion yet for this question.