For effective VMware platform validation to take place, that platform should be _____________.

The correct answer is B. running workloads of projected application resource requirements. A validation plan can range from a detailed test plan to high-level statements. It should not be subjective. The best validation is to place a platform under a typical test of what it will be faced with in the field --for example, having a simulated number of users go through a…

Create a Design for vSphere 5.x Management and Monitoring

Question

For effective VMware platform validation to take place, that platform should be _____________.

Options

  • Arunning test guest workloads
  • Brunning workloads of projected application resource requirements
  • Cstress tested until failure to understand capacity

How the community answered

(20 responses)
  • A
    10% (2)
  • B
    80% (16)
  • C
    10% (2)

Explanation

A validation plan can range from a detailed test plan to high-level statements. It should not be subjective. The best validation is to place a platform under a typical test of what it will be faced with in the field --for example, having a simulated number of users go through a workflow (perhaps a website). A lot of these tasks vary with the type of application and are primarily application functionality based. In addition, platform or infrastructure metrics are key for validation and for information to be used within the operational documentation (for example, troubleshooting guide, monitoring recommendations).