nerdexam
Broadcom-VMware

VCPD510 · Question #391

A View administrator is creating a linked clone pool of desktops that delete or refresh after logoff. Which storage overcommit level should be used to maximize use of the datastore while retaining a…

The correct answer is D. Moderate. See the full explanation below for the reasoning.

Question

A View administrator is creating a linked clone pool of desktops that delete or refresh after logoff. Which storage overcommit level should be used to maximize use of the datastore while retaining a reserve?

Options

  • AConservative
  • BAggressive
  • CNone
  • DModerate

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    12% (3)
  • D
    81% (21)

Community Discussion

No community discussion yet for this question.

Full VCPD510 Practice