An administrator would like to have vCenter take action any time a virtual machine is using over 90% of its available resources for five minutes or longer. Which three actions can be taken by…
The correct answer is A. Power on a VM B. Reboot Guest on VM D. Migrate a VM. See the full explanation below for the reasoning.
Question
An administrator would like to have vCenter take action any time a virtual machine is using over 90% of its available resources for five minutes or longer. Which three actions can be taken by vCenter Server in response to the trigger without running a script? (Choose three.)
Options
- APower on a VM
- BReboot Guest on VM
- CIncrease Virtual Machine Memory
- DMigrate a VM
- EIncrease Virtual Machine CPU Shares
How the community answered
(66 responses)- A83% (55)
- C6% (4)
- E11% (7)