A vSphere 5 implementation consists of a fully automated DRS cluster with two ESXi 5.x hosts with the following vSphere Standard Switch configuration: 1. Switch A. three vmnics, one port group named…

The correct answer is B. Move a vmnic from Switch A to Switch B on each host. See the full explanation below for the reasoning.

Question

A vSphere 5 implementation consists of a fully automated DRS cluster with two ESXi 5.x hosts with the following vSphere Standard Switch configuration: 1. Switch A. three vmnics, one port group named sFTP-PG 2. Switch B. two vmnics, one port group named Web-PG 3. All vmnics are trunked to the same physical switch. DRS has been configured with an anti-affinity rule for all virtual machines in the Web-PG so that no more than half of the virtual machines run on any given host. The virtual machines on WebPG are experiencing significant network latency. The network team has determined that a performance bottleneck is occurring at the ESXi host level. Which solution will require the least amount of administrative work and the least amount of service interruption?

Options

  • AMigrate Web-PG to Switch A and sFTP-PG to Switch B on each host
  • BMove a vmnic from Switch A to Switch B on each host
  • CConvert the three Switch Bs to a single vSphere Distributed Switch
  • DUse vMotion to redistribute some of the VMs in Web-PG to a different ESXi host

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    80% (16)
  • C
    10% (2)
  • D
    5% (1)