Your Cloud Administrator has asked you to deploy an Edge Gateway that will serve as a primary gateway for multiple Org vDC Networks. It has been decided that the size of the Edge Gateway will be…

The correct answer is C. 2 cpu(s) with 2000 Shares and 1024MB of memory. See the full explanation below for the reasoning.

Question

Your Cloud Administrator has asked you to deploy an Edge Gateway that will serve as a primary gateway for multiple Org vDC Networks. It has been decided that the size of the Edge Gateway will be Full. When the Edge Gateway is deployed, what is the correct number cpus, memory, and cpu shares that will be automatically allocated?

Options

  • A1 cpu(s) with 1000 Shares and 256MB of memory.
  • B2 cpu(s) with 1000 Shares and 512MB of memory.
  • C2 cpu(s) with 2000 Shares and 1024MB of memory.
  • D1 cpu(s) with 2000 Shares and 256MB of memory.

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    77% (20)
  • D
    15% (4)