nerdexam
Broadcom-VMware

VCPC510 · Question #131

An organization builds a new datacenter containing vSphere clusters and a new vCenter Server. The organization needs to add a new vCD cell to the existing architecture. What must be done to achieve…

The correct answer is A. Complete the configuration of vCloud Director and vShield Manager at the new datacenter. See the full explanation below for the reasoning.

Question

An organization builds a new datacenter containing vSphere clusters and a new vCenter Server. The organization needs to add a new vCD cell to the existing architecture. What must be done to achieve this?

Options

  • AComplete the configuration of vCloud Director and vShield Manager at the new datacenter.
  • BAttach the new vCenter Server from the Administration tab in the vCloud Director GUI.
  • CEnable linked mode for the vCenter Servers, then register the new vCenter Server with the existing
  • DComplete the configuration of vCloud Director at the new datacenter and enable linked mode for the

How the community answered

(29 responses)
  • A
    76% (22)
  • B
    14% (4)
  • C
    3% (1)
  • D
    7% (2)

Community Discussion

No community discussion yet for this question.

Full VCPC510 Practice