VCP510 · Question #121

What are three true statements about an integrity check in vCenter Data Recovery? (Choose three.)

The correct answer is B. The operation is scheduled separately form the backup schedule. D. The operation automatically pauses when the end of the maintenance widow is reached E. By default the operation does not run during normal business hours. When you do integrity check in vcenter data recovery, you can schedule the operation separately from the backup schedule. When the end of the maintenance window is reached operation is paused automatically. Along with this, the operation does not run during normal business hours

Establish and Maintain Service Levels

Question

What are three true statements about an integrity check in vCenter Data Recovery? (Choose three.)

Options

  • AThe operation is prevented from overlaping with the backup operations.
  • BThe operation is scheduled separately form the backup schedule.
  • CAn incremental operation can be manually started.
  • DThe operation automatically pauses when the end of the maintenance widow is reached
  • EBy default the operation does not run during normal business hours.

How the community answered

(51 responses)
  • A
    14% (7)
  • B
    80% (41)
  • C
    6% (3)

Explanation

When you do integrity check in vcenter data recovery, you can schedule the operation separately from the backup schedule. When the end of the maintenance window is reached operation is paused automatically. Along with this, the operation does not run during normal business hours

Topics

#vCenter Data Recovery#integrity check#backup schedule#maintenance window