nerdexam
Broadcom-VMware

VCAC510 · Question #16

Your development team has informed you that they frequently run tests which require three VMs and take two days to run. When the tests are complete, there is no further need to keep the VMs or the…

The correct answer is D. vCloud Automation Center. See the full explanation below for the reasoning.

Question

Your development team has informed you that they frequently run tests which require three VMs and take two days to run. When the tests are complete, there is no further need to keep the VMs or the resources they have been consuming. Which of the following products would best help you manage the requirements of this test environment?

Options

  • AvCloud Director
  • BvFabric Suite
  • CvCenter Orchestrator
  • DvCloud Automation Center

How the community answered

(54 responses)
  • A
    4% (2)
  • B
    11% (6)
  • C
    6% (3)
  • D
    80% (43)

Community Discussion

No community discussion yet for this question.

Full VCAC510 Practice