Your manager is planning next year's capital expense budget and asks if it's possible to know when the infrastructure components in your cloud will run out of capacity and therefore need upgrading…
The correct answer is D. Risk. See the full explanation below for the reasoning.
Question
Your manager is planning next year's capital expense budget and asks if it's possible to know when the infrastructure components in your cloud will run out of capacity and therefore need upgrading. You tell him you can get that information using vCenter Operations Manager. Which vCenter Operations Manager Super Metric badge would you look under to see the time remaining and capacity remaining for your infrastructure components?
Options
- APerformance
- BEfficiency
- CHealth
- DRisk
How the community answered
(27 responses)- A11% (3)
- B4% (1)
- C4% (1)
- D81% (22)