EXIN
TMPTE · Question #37
There are two parties in the V model: the supplying party the accepting party Which system development phase or test phase is not performed by the supplying party? EXIN TMPTE Exam
The correct answer is D. Technical design. See the full explanation below for the reasoning.
Question
There are two parties in the V model:
the supplying party the accepting party Which system development phase or test phase is not performed by the supplying party? EXIN TMPTE Exam
Options
- AFunctional design
- BRealization
- CSystem test
- DTechnical design
How the community answered
(58 responses)- A14% (8)
- B5% (3)
- C3% (2)
- D78% (45)
Community Discussion
No community discussion yet for this question.