Question
A contractor is conducting training for a company. After arriving, the contractor realizes that the room assigned for training is missing a required element (e.g. projector, screen, etc.). The contractor is frustrated because the client was aware of the needed equipment in ample time. Which of the following is the FIRST course of action?
Options
- ACancel the training
- BNotify the appropriate people
- CTeach the course
- DDelay the training
How the community answered
(56 responses)- A5% (3)
- B84% (47)
- C2% (1)
- D9% (5)