SY0-701 · Question #914
SY0-701 Question #914: Real Exam Question with Answer & Explanation
The correct answer is A: Key risk indicators. A risk register is a catalog of identified risks and their details; for each entry you track signals that a risk is materializing. Those measurable signals are key risk indicators (KRIs) - thresholds or metrics (e.g., failed logins/day, patch backlog age) tied to a specific risk
Question
Which of the following is a component of a risk register?
Options
- AKey risk indicators
- BContinuous risk assessment
- CRisk appetite
- DRisk culture
Explanation
A risk register is a catalog of identified risks and their details; for each entry you track signals that a risk is materializing. Those measurable signals are key risk indicators (KRIs) - thresholds or metrics (e.g., failed logins/day, patch backlog age) tied to a specific risk so you can spot escalation early and trigger the planned response. Continuous assessment, appetite, and culture are program-level concepts, not individual register fields.
Community Discussion