SY0-701 · Question #202

SY0-701 Question #202: Real Exam Question with Answer & Explanation

The correct answer is A: Estimating the recovery time of systems. Estimating the recovery time of systems is a task typically included in the Business Impact Analysis (BIA) process. BIA involves identifying the critical functions of a business and determining the impact of a disruption. This includes estimating how long it will take to recover

Submitted by parkjh· Mar 6, 2026Security program management and oversight

Question

Which of the following tasks is typically included in the BIA process?

Options

  • AEstimating the recovery time of systems
  • BIdentifying the communication strategy
  • CEvaluating the risk management plan
  • DEstablishing the backup and recovery procedures
  • EDeveloping the incident response plan

Explanation

Estimating the recovery time of systems is a task typically included in the Business Impact Analysis (BIA) process. BIA involves identifying the critical functions of a business and determining the impact of a disruption. This includes estimating how long it will take to recover systems and resume normal operations. Estimating the recovery time of systems: A key component of BIA, which helps in understanding the time needed to restore systems and services after a disruption. Identifying the communication strategy: Typically part of the incident response plan, not BIA. Evaluating the risk management plan: Part of risk management, not specifically BIA. Establishing the backup and recovery procedures: Important for disaster recovery, not directly part of BIA. Developing the incident response plan: Focuses on responding to security incidents, not on the impact analysis.