A company is developing a business continuity strategy and needs to determine how many staff members would be required to sustain the business in the case of a disruption. Which of the following…

The correct answer is A. Capacity planning. Capacity planning is the process of determining the resources needed to meet the current and future demands of an organization. Capacity planning can help a company develop a business continuity strategy by estimating how many staff members would be required to sustain the…

Submitted by chen.hong· Mar 6, 2026Security program management and oversight

Question

A company is developing a business continuity strategy and needs to determine how many staff members would be required to sustain the business in the case of a disruption. Which of the following best describes this step?

Options

  • ACapacity planning
  • BRedundancy
  • CGeographic dispersion
  • DTablet exercise

How the community answered

(27 responses)
  • A
    70% (19)
  • B
    7% (2)
  • C
    19% (5)
  • D
    4% (1)

Explanation

Capacity planning is the process of determining the resources needed to meet the current and future demands of an organization. Capacity planning can help a company develop a business continuity strategy by estimating how many staff members would be required to sustain the business in the case of a disruption, such as a natural disaster, a cyberattack, or a pandemic. Capacity planning can also help a company optimize the use of its resources, reduce costs, and improve performance.