SY0-701 · Question #1078

SY0-701 Question #1078: Real Exam Question with Answer & Explanation

The correct answer is D: Change management procedures. Change management procedures enforce formal review, approval, testing, and scheduling of software changes, ensuring releases are controlled, documented, and deployed in an orderly

Submitted by anjalisingh· Mar 6, 2026Security program management and oversight

Question

Which of the following will best ensure a controlled version release of a new software application?

Options

  • ABusiness continuity planning
  • BQuantified risk analysis
  • CStatic code analysis
  • DChange management procedures

Explanation

Change management procedures enforce formal review, approval, testing, and scheduling of software changes, ensuring releases are controlled, documented, and deployed in an orderly