Joe, the system administrator, is performing an overnight system refresh of hundreds of user computers. The refresh has a strict timeframe and must have zero downtime during business hours. Which of…

The correct answer is D. A back-out strategy planned out anticipating any unforeseen problems that may arise. A back-out strategy (rollback plan) is essential when performing large-scale changes under a strict timeframe. If something goes wrong during the overnight refresh, a back-out plan allows Joe to quickly revert systems to their previous working state before business hours begin…

Security operations

Question

Joe, the system administrator, is performing an overnight system refresh of hundreds of user computers. The refresh has a strict timeframe and must have zero downtime during business hours. Which of the following should Joe take into consideration?

Options

  • AA disk-based image of every computer as they are being replaced.
  • BA plan that skips every other replaced computer to limit the area of affected users.
  • CAn offsite contingency server farm that can act as a warm site should any issues appear.
  • DA back-out strategy planned out anticipating any unforeseen problems that may arise.

How the community answered

(63 responses)
  • A
    6% (4)
  • B
    13% (8)
  • C
    3% (2)
  • D
    78% (49)

Explanation

A back-out strategy (rollback plan) is essential when performing large-scale changes under a strict timeframe. If something goes wrong during the overnight refresh, a back-out plan allows Joe to quickly revert systems to their previous working state before business hours begin, ensuring zero downtime. Taking disk images of every replaced computer is a good practice but does not address the risk of the refresh failing mid-task. Skipping every other computer is not a risk mitigation strategy. An offsite warm site is for disaster recovery scenarios, not a planned maintenance window. A solid back-out strategy is the primary safeguard for change management operations with hard deadlines.

Topics

#change management#back-out plan#business continuity#risk mitigation