Pete, the system administrator, is reviewing his disaster recovery plans. He wishes to limit the downtime in the event of a disaster, but does not have the budget approval to implement or maintain…

The correct answer is A. Use hardware already at an offsite location and configure it to be quickly utilized. This describes a warm site - a pre-configured offsite location with hardware ready to be brought online quickly, balancing cost and recovery time. A hot site (99.99% availability) is too expensive. Option B (moving to another part of the same campus) doesn't protect against a…

Security operations

Question

Pete, the system administrator, is reviewing his disaster recovery plans. He wishes to limit the downtime in the event of a disaster, but does not have the budget approval to implement or maintain an offsite location that ensures 99.99% availability. Which of the following would be Pete's BEST option?

Options

  • AUse hardware already at an offsite location and configure it to be quickly utilized.
  • BMove the servers and data to another part of the company's main campus from the server room.
  • CRetain data back-ups on the main campus and establish redundant servers in a virtual environment.
  • DMove the data back-ups to the offsite location, but retain the hardware on the main campus for redundancy.

How the community answered

(22 responses)
  • A
    73% (16)
  • B
    18% (4)
  • C
    5% (1)
  • D
    5% (1)

Explanation

This describes a warm site - a pre-configured offsite location with hardware ready to be brought online quickly, balancing cost and recovery time. A hot site (99.99% availability) is too expensive. Option B (moving to another part of the same campus) doesn't protect against a site-wide disaster. Option C (virtual environment on the main campus) still risks total loss if the campus is destroyed. Option D (only moving data offsite but keeping hardware on-site) still loses hardware in a disaster. A warm site is the cost-effective middle ground.

Topics

#disaster recovery#warm site#business continuity#offsite location

Community Discussion

No community discussion yet for this question.