SY0-301 · Question #106
SY0-301 Question #106: Real Exam Question with Answer & Explanation
The correct answer is D: IT Contingency Plan. An IT Contingency Plan is the most specific plan, addressing detailed procedures for various specific IT system problems and failure scenarios. A Business Continuity Plan (BCP) is broad and covers the entire organization's ability to continue operations. A Continuity of Operation
Question
Options
- ABusiness Continuity Plan
- BContinuity of Operation Plan
- CDisaster Recovery Plan
- DIT Contingency Plan
Explanation
An IT Contingency Plan is the most specific plan, addressing detailed procedures for various specific IT system problems and failure scenarios. A Business Continuity Plan (BCP) is broad and covers the entire organization's ability to continue operations. A Continuity of Operations Plan (COOP) focuses on maintaining essential functions across the organization, also broadly scoped. A Disaster Recovery Plan (DRP) focuses on recovering IT systems after a major disaster but is less granular than a contingency plan. The IT Contingency Plan drills down to specific system-level issues and step-by-step responses.
Community Discussion