Symantec
ST0-172 · Question #45
A Symantec NetBackup administrator has an environment that runs over one thousand jobs a night. Some nights there are hundreds of jobs queued waiting for a resource. Which action should the administra
The correct answer is C. increment the job priority in the activity monitor for the job. See the full explanation below for the reasoning.
Question
A Symantec NetBackup administrator has an environment that runs over one thousand jobs a night. Some nights there are hundreds of jobs queued waiting for a resource. Which action should the administrator take in the event that specific jobs need to run when a resource next becomes available during that evening's backup session?
Options
- Apause all queued jobs except for the job that needs to run
- Bchange the job priority for the job in the policy
- Cincrement the job priority in the activity monitor for the job
- Dcancel the job and the restart the job after changing the policy job priority
How the community answered
(33 responses)- A9% (3)
- B3% (1)
- C73% (24)
- D15% (5)
Community Discussion
No community discussion yet for this question.