SSCP · Question #483

Which of the following enables the person responsible for contingency planning to focus risk management efforts and resources in a prioritized manner only on the identified risks?

The correct answer is A. Risk assessment. The risk assessment is critical because it enables the person responsible for contingency planning to focus risk management efforts and resources in a prioritized manner only on the identified risks. The risk management process includes the risk assessment and determination of…

Submitted by carter_n· Apr 18, 2026Risk Identification, Monitoring and Analysis

Question

Which of the following enables the person responsible for contingency planning to focus risk management efforts and resources in a prioritized manner only on the identified risks?

Options

  • ARisk assessment
  • BResidual risks
  • CSecurity controls
  • DBusiness units

How the community answered

(16 responses)
  • A
    88% (14)
  • B
    6% (1)
  • C
    6% (1)

Explanation

The risk assessment is critical because it enables the person responsible for contingency planning to focus risk management efforts and resources in a prioritized manner only on the identified risks. The risk management process includes the risk assessment and determination of suitable technical, management, and operational security controls based on the level of threat the risk imposes. Business units should be included in this process.

Topics

#Risk Management#Risk Assessment#Contingency Planning#Prioritization