Risk reduction in a system development life-cycle should be applied:

The correct answer is D. Equally to all phases. Risk management is a continuous, lifecycle-wide activity. Each SDLC phase introduces its own unique risks: Initiation has requirement risks, Development has coding and design risks, Implementation has configuration and integration risks, Operation has operational and…

Submitted by obi.ng· Apr 18, 2026Systems and Application Security

Question

Risk reduction in a system development life-cycle should be applied:

Options

  • AMostly to the initiation phase.
  • BMostly to the development phase.
  • CMostly to the disposal phase.
  • DEqually to all phases.

How the community answered

(38 responses)
  • A
    5% (2)
  • C
    3% (1)
  • D
    92% (35)

Explanation

Risk management is a continuous, lifecycle-wide activity. Each SDLC phase introduces its own unique risks: Initiation has requirement risks, Development has coding and design risks, Implementation has configuration and integration risks, Operation has operational and environmental risks, and Disposal has data remnant risks. Concentrating risk reduction in only one phase leaves the others exposed. Best practice mandates that risk assessment and mitigation be applied equally and consistently across all phases.