SOFA-CFE · Question #196
Which phase subjects a capital expenditure proposal to review by all departments capable of passing judgment on the procedural aspects?
The correct answer is C. technical evaluation phase. Option C is correct because the technical evaluation phase is specifically designed to subject a capital expenditure proposal to scrutiny from all relevant departments that can assess its procedural, operational, and technical soundness - engineering, procurement, operations…
Question
Which phase subjects a capital expenditure proposal to review by all departments capable of passing judgment on the procedural aspects?
Options
- APlanning phase
- BModeling phase
- Ctechnical evaluation phase
- Deconomic criterion phase
How the community answered
(39 responses)- A3% (1)
- B10% (4)
- C82% (32)
- D5% (2)
Explanation
Option C is correct because the technical evaluation phase is specifically designed to subject a capital expenditure proposal to scrutiny from all relevant departments that can assess its procedural, operational, and technical soundness - engineering, procurement, operations, and others each weigh in on whether the proposal is executable and compliant with established procedures.
Why the distractors are wrong:
- A (Planning): The planning phase is where the need or idea is first identified and the proposal is drafted - it precedes any formal departmental review.
- B (Modeling): A modeling phase focuses on building simulations or financial/operational models, not cross-departmental procedural review.
- D (Economic criterion): This phase evaluates financial metrics like NPV, IRR, or payback period - it's about money, not procedural assessment.
Memory tip: Think "Technical = Team review" - the technical evaluation phase is where the team of departments checks whether the proposal actually works procedurally before anyone commits resources.