SG0-001 · Question #488

A datacenter has 100 TB of Tier 1 storage, 600 TB of Tier 2 storage and a large tape library. HSM is moving data from Tier 1 to Tier 2 at the rate of 5 TB per month, while 10% of Tier 2 data is transf

The correct answer is A. 0 TB. The data flow analysis shows that the amount of data moved into Tier 2 is balanced by the amount of data moved out of Tier 2 to tape, resulting in no net increase in Tier 2 storage over two years.

Storage Management

Question

A datacenter has 100 TB of Tier 1 storage, 600 TB of Tier 2 storage and a large tape library. HSM is moving data from Tier 1 to Tier 2 at the rate of 5 TB per month, while 10% of Tier 2 data is transferred to tape per year. The storage administrator is asked to forecast the amount of new Tier 2 storage that will be needed over the next two years. Which of the following does the administrator report?

Options

  • A0 TB
  • B5 TB
  • C60 TB
  • D120 TB

How the community answered

(59 responses)
  • A
    56% (33)
  • B
    7% (4)
  • C
    12% (7)
  • D
    25% (15)

Why each option

The data flow analysis shows that the amount of data moved into Tier 2 is balanced by the amount of data moved out of Tier 2 to tape, resulting in no net increase in Tier 2 storage over two years.

A0 TBCorrect

Data moves from Tier 1 to Tier 2 at 5 TB/month, totaling 60 TB/year (5 TB * 12 months). Concurrently, 10% of the 600 TB Tier 2 data, which is 60 TB/year (0.10 * 600 TB), is moved to tape. Since the inflow into Tier 2 (60 TB/year) equals the outflow from Tier 2 (60 TB/year), there is no net increase in Tier 2 storage needed, meaning 0 TB over two years.

B5 TB

This answer incorrectly assumes a minimal net increase or miscalculates the annual balance; it does not account for the equilibrium achieved by data moving to tape.

C60 TB

This answer calculates the total data moved from Tier 1 to Tier 2 over one year (5 TB/month * 12 months = 60 TB) but neglects to subtract the data moved out of Tier 2 to tape.

D120 TB

This answer calculates the total data moved from Tier 1 to Tier 2 over two years (5 TB/month * 24 months = 120 TB) but fails to account for the substantial amount of data moving out of Tier 2 to tape during that period.

Concept tested: Storage capacity planning and data lifecycle

Topics

#storage capacity planning#tiered storage#HSM#data migration

Community Discussion

No community discussion yet for this question.

Full SG0-001 Practice