SAFE-SPC · Question #52

A Program Epic that originates from a Portfolio Epic takes precedence over all local priorities on that train.

The correct answer is B. False. Option B is correct because in SAFe, a Program Epic that originates from a Portfolio Epic still enters the Program Backlog and must be prioritized alongside other work using standard methods like WSJF (Weighted Shortest Job First) - its portfolio origin does not grant it…

Portfolio Management and Epic Flow

Question

A Program Epic that originates from a Portfolio Epic takes precedence over all local priorities on that train.

Options

  • ATrue
  • BFalse

How the community answered

(26 responses)
  • A
    12% (3)
  • B
    88% (23)

Explanation

Option B is correct because in SAFe, a Program Epic that originates from a Portfolio Epic still enters the Program Backlog and must be prioritized alongside other work using standard methods like WSJF (Weighted Shortest Job First) - its portfolio origin does not grant it automatic precedence over local priorities on the ART. The ART maintains its own prioritization authority; the source of an epic does not bypass the train's PI Planning and backlog refinement process. Option A is wrong because SAFe explicitly decentralizes decision-making and preserves the ART's autonomy - no epic automatically overrides local prioritization simply due to its origin.

Memory tip: Think of it this way - origin ≠ urgency. A Portfolio Epic spawning a Program Epic is like a corporate mandate becoming a local project; it still has to get in line and be prioritized on its merits, not just because of where it came from.

Topics

#Epic hierarchy#portfolio epics#program epics#local priorities