SAFE-SPC · Question #45

AFe assumes that programs commit to the key priorities within the current PI and provide a forecast for a few subsequent PIs.

The correct answer is A. True. Option A is correct because in SAFe (Scaled Agile Framework), PI Planning operates on a dual-horizon model: teams make firm commitments to the highest-priority features and objectives within the current PI, while providing a looser, directional forecast for the next two or more…

Agile Release Train and PI Planning

Question

AFe assumes that programs commit to the key priorities within the current PI and provide a forecast for a few subsequent PIs.

Options

  • ATrue
  • BFalse

How the community answered

(35 responses)
  • A
    94% (33)
  • B
    6% (2)

Explanation

Option A is correct because in SAFe (Scaled Agile Framework), PI Planning operates on a dual-horizon model: teams make firm commitments to the highest-priority features and objectives within the current PI, while providing a looser, directional forecast for the next two or more upcoming PIs. This structure gives stakeholders confidence in near-term delivery while maintaining visibility into the longer-term roadmap. Option B (False) is incorrect because this commit-now/forecast-later approach is a foundational element of SAFe's PI Planning ceremony - it is explicitly built into the process, not optional or absent.

Memory tip: Think of it as a "commit close, forecast far" rule - like booking a hotel: you confirm your room for tonight (current PI) but only roughly plan where you'll stay next month (future PIs).

Topics

#PI Planning#ART commitment#PI forecast#program priorities