(Select 2) SAFe teams using Kanban are required to participate in which events?

The correct answer is C. System Demo D. PI Planning. In SAFe, Kanban teams operate without fixed-length iterations, so they skip time-boxed Scrum ceremonies. However, they still participate in PI Planning (D) and System Demo (C) because these are Agile Release Train (ART)-level events that all teams on the train must attend…

Team Level / Agile Teams

Question

(Select 2) SAFe teams using Kanban are required to participate in which events?

Options

  • AIteration Planning
  • BIteration Retrospective
  • CSystem Demo
  • DPI Planning

How the community answered

(56 responses)
  • A
    5% (3)
  • B
    2% (1)
  • C
    93% (52)

Explanation

In SAFe, Kanban teams operate without fixed-length iterations, so they skip time-boxed Scrum ceremonies. However, they still participate in PI Planning (D) and System Demo (C) because these are Agile Release Train (ART)-level events that all teams on the train must attend, regardless of their team-level process.

Iteration Planning (A) and Iteration Retrospective (B) are Scrum-specific ceremonies tied to fixed sprints - since Kanban teams don't work in iterations, these events don't apply to them.

Memory tip: Think of it as two levels - team-level events (Planning, Retro) belong to Scrum teams only, while ART-level events (PI Planning, System Demo) are mandatory for every team on the train, Scrum or Kanban alike.

Topics

#Team Kanban#SAFe events#System Demo#PI Planning participation