What is the SAFe calculation for Weighted Shortest Job First?

The correct answer is A. (User/Business Value + Time Criticality + Opportunity Enablement/Risk Reduction)/Job Size. Option A correctly represents the SAFe WSJF formula: Cost of Delay divided by Job Size, where Cost of Delay is the sum of three components - User/Business Value, Time Criticality, and Risk Reduction/Opportunity Enablement. These three factors capture why delay is costly, and…

Lean Portfolio Management / Prioritization

Question

What is the SAFe calculation for Weighted Shortest Job First?

Options

  • A(User/Business Value + Time Criticality + Opportunity Enablement/Risk Reduction)/Job Size.
  • B(Risk Reduction/Opportunity Enablement + Time Criticality + Size)/Business Value.
  • C(User/Business Value + Size + Risk Reduction/Opportunity Enablement)/Job Size.
  • D(User/Business Value + Size + Risk Reduction/Opportunity Enablement)/Time.

How the community answered

(31 responses)
  • A
    94% (29)
  • B
    3% (1)
  • D
    3% (1)

Explanation

Option A correctly represents the SAFe WSJF formula: Cost of Delay divided by Job Size, where Cost of Delay is the sum of three components - User/Business Value, Time Criticality, and Risk Reduction/Opportunity Enablement. These three factors capture why delay is costly, and dividing by Job Size (duration/effort) prioritizes the highest-value, shortest work first.

Why the distractors fail:

  • B is wrong because it places Business Value in the denominator - the opposite of its role - and shuffles the Cost of Delay components incorrectly.
  • C is wrong because it swaps Time Criticality out of the numerator and replaces it with Size, which belongs in the denominator.
  • D is wrong because it divides by Time rather than Job Size (effort/duration); time is already captured within the Time Criticality component of Cost of Delay.

Memory tip: Think of WSJF as a fraction where the top (numerator) answers "Why is waiting costly?" - Value + Urgency + Risk - and the bottom answers "How big is the job?". The acronym VUR/S (Value, Urgency, Risk over Size) can help you reconstruct the formula under pressure.

Topics

#WSJF formula#cost of delay#economic framework#prioritization