SAFE-SPC · Question #127
(Select 3) Which of the following have acceptance criteria?
The correct answer is A. Business Capabilities D. Enabler Features E. Spikes. In SAFe, acceptance criteria belong to items that represent deliverable, verifiable work: Business Capabilities (large-solution-level work items verified by acceptance tests), Enabler Features (PI-level work with defined done conditions), and Spikes (time-boxed research stories…
Question
(Select 3) Which of the following have acceptance criteria?
Options
- ABusiness Capabilities
- BPortfolio Enabler Epics
- CStrategic Themes
- DEnabler Features
- ESpikes
- FProgram Epics
How the community answered
(46 responses)- A78% (36)
- B13% (6)
- C7% (3)
- F2% (1)
Explanation
In SAFe, acceptance criteria belong to items that represent deliverable, verifiable work: Business Capabilities (large-solution-level work items verified by acceptance tests), Enabler Features (PI-level work with defined done conditions), and Spikes (time-boxed research stories whose acceptance criteria describe what question must be answered or artifact produced).
Distractors: Portfolio Enabler Epics (B) and Program Epics (F) are governed by a Lean Business Case, not acceptance criteria - they are too large and uncertain to be accepted as-is; they get decomposed into Features/Capabilities that do carry acceptance criteria. Strategic Themes (C) are enterprise-level objectives that provide portfolio direction, not backlog items at all, so they have no acceptance criteria.
Memory tip: Ask "Can this item be accepted as done in a PI?" - if yes, it needs acceptance criteria. Epics are always too big (they decompose first), and Strategic Themes are never "done." Think: CAFeS - Capabilities, featurEs (And enabler variants), and Spikes all carry acceptance criteria.
Topics