SAFE-SP · Question #79
What is one responsibility of the Scrum Master?
The correct answer is C. To remove impediments in order to help protect the team. Removing impediments is a core Scrum Master responsibility - they act as a servant-leader who shields the team from obstacles (organizational bottlenecks, blocked dependencies, interpersonal conflicts) so the team can focus on delivering value. A is wrong because prioritizing…
Question
What is one responsibility of the Scrum Master?
Options
- ATo prioritize the Team's Backlog
- BTo define the tasks and assign owners
- CTo remove impediments in order to help protect the team
- DTo facilitate the PI Planning session
How the community answered
(41 responses)- A2% (1)
- B7% (3)
- C88% (36)
- D2% (1)
Explanation
Removing impediments is a core Scrum Master responsibility - they act as a servant-leader who shields the team from obstacles (organizational bottlenecks, blocked dependencies, interpersonal conflicts) so the team can focus on delivering value. A is wrong because prioritizing the backlog is the Product Owner's job. B is wrong because self-organizing teams define their own tasks and assign owners - the Scrum Master doesn't dictate this. D is wrong because PI Planning facilitation belongs to the Release Train Engineer (RTE) in SAFe, not the Scrum Master.
Memory tip: Think of the Scrum Master as a "shield and servant" - they serve the team by shielding them from anything that slows progress. If an answer describes assigning, prioritizing, or planning for the team, it's the wrong role.
Topics