SAFE-SP · Question #61
Iteration planning, Iteration review, and backlog refinement are examples of which type of event
The correct answer is B. Team event. Iteration Planning, Iteration Review, and Backlog Refinement are Team events in SAFe (Scaled Agile Framework) because they occur at the Agile Team level within a single iteration (sprint) cadence - they involve only the team itself, not the broader program or train. Why the…
Question
Iteration planning, Iteration review, and backlog refinement are examples of which type of event
Options
- API event
- BTeam event
- CSync event
- DProgram event
How the community answered
(56 responses)- A2% (1)
- B93% (52)
- C2% (1)
- D4% (2)
Explanation
Iteration Planning, Iteration Review, and Backlog Refinement are Team events in SAFe (Scaled Agile Framework) because they occur at the Agile Team level within a single iteration (sprint) cadence - they involve only the team itself, not the broader program or train.
Why the distractors are wrong:
- A (PI event): PI (Program Increment) events span multiple teams and multiple iterations - e.g., PI Planning and the Inspect & Adapt workshop operate at the ART level across ~10 weeks, not within a single team's iteration.
- C (Sync event): Sync events (like Scrum of Scrums or ART Sync) are coordination touchpoints between teams or roles, not team-internal ceremonies.
- D (Program event): Program events involve the full Agile Release Train (ART) - e.g., System Demo - not a single team's workflow.
Memory tip: Think "T" for Team = small scope. If the event happens inside one team's iteration box on the SAFe Big Picture, it's a Team event. If it spans teams or the whole train, it's Program or PI.