The Inspect and Adapt event always starts with which activity?

The correct answer is A. The PI System Demo. A is correct because the SAFe Inspect and Adapt event follows a fixed three-part sequence, and the PI System Demo always comes first - teams and stakeholders gather to see a live demonstration of all the working features integrated across the Agile Release Train during the PI…

Inspect and Adapt

Question

The Inspect and Adapt event always starts with which activity?

Options

  • AThe PI System Demo
  • BAgreement on the problems to solve
  • CQuantitative measurement
  • DRetrospective and Problem Solving Workshop

How the community answered

(42 responses)
  • A
    95% (40)
  • C
    2% (1)
  • D
    2% (1)

Explanation

A is correct because the SAFe Inspect and Adapt event follows a fixed three-part sequence, and the PI System Demo always comes first - teams and stakeholders gather to see a live demonstration of all the working features integrated across the Agile Release Train during the PI. C (Quantitative measurement) is the second activity, where the ART measures its actual vs. planned velocity and other metrics after seeing the demo. D (Retrospective and Problem Solving Workshop) is the third and final activity, not the first - it uses the insight from the demo and metrics to identify and solve systemic problems. B (Agreement on the problems to solve) is a step within the Retrospective workshop, not a standalone opening activity.

Memory tip: Think of I&A as "Show → Measure → Fix" - you always show the work first (PI System Demo), measure how you did, then fix what's broken in the Retrospective. The order mirrors natural post-work reflection: see it, score it, improve it.

Topics

#Inspect and Adapt#PI System Demo#SAFe ceremonies#event structure